Scope of Supply: PUMPS, SERVICING
In the Year 1996 Western Energy secured a contract for CCR Upgrading project at Exxon Mobil refinery in Singapore, earlier Mobil Oil.
Total of 21 units of API 610 Process Pumps were upgraded including pump overhaul, change out of impellers, wear rings and motors in addition to base plate modifications. This upgrading was executed on a very urgent basis such as 4 units of pumps were undergoing above mentioned servicing within one week time.
All modifications as well as servicing took place at Western Energy workshop in Tuas area.